Scope of Works

The scope of works will incorporate the following:

  • Back straight to be widened to suit overall track
  • Existing sand track to be realigned on back straight
  • New 8m wide sand track
  • New public facility
  • Additional swab stall
  • Existing turf track to be reconstructed
  • New tie up stalls
  • New jockeys and stewards facility
  • New mounting yard and horse pathway
  • Replace major drainage culvert
  • Removal of the grandstand
  • Revised car park layout and resurface
  • Installation of training lights

Project Budget - $8.2m

Beaudesert New Plan

Latest update

DATE

UPDATE

21 March 2012

State Government approves funding deed for Industry Infrastructure Plan (IIP).

Media Release

1 February 2012

The Queensland Government and Racing Queensland Limited (RQL) today unveiled significant changes to the $110 million Industry Infrastructure Plan (IIP) including details of the $8.2 million Beaudesert Race Club upgrade.

For further information click here

25 January 2012

Beaudesert project business case lodged with Treasury.

11 November 2011

Racing Queensland and representatives from the Beaudesert Race Club met today to discuss the following key issues relative to the Beaudesert Industry Infrastructure Project.

  • Project Budget & Scope of Works
  • Finalisation of Business Case
  • Forecast Commencement Date
  • Impact on Racing and Training Schedule

Click here for an overview of the current status of each of the aforementioned areas.

4 November 2011

RQL is in the final stages of compiling the Beaudesert project business case to be lodged with the Office of Racing for their review.

1 November 2011

The civil works at the Beaudesert site will be classed as track maintenance and will not require council development applications.

 

 *Click the i for details about the image



Beaudesert Plan23 February, Beaudesert’s tie-up stalls in worn condition prior to commencement of works.23 February, Old mounting yard just prior to commencement of works.23 February, Broadcast tower and out-dated public and stakeholder facilities.23 February, Beaudesert’s grandstand in a worn state just prior to commencement of works. 23 February, Beaudesert course proper prior to commencement of works.23 February, Original Beaudesert facilities just prior to commencement of works.