Completed

The project entailed removing the reverse camber from the 500m to the 900m and the 1100m to the 1500m, installation and rectification of the inside/outside rail, installation of additional surface drainage improvements to the track and installation of a new water bore that will provide water to the facility and broader community use.

 

Innisfail-3.jpg

Project Timeline

Year Action
June 2019 CRP Funding Approval – Round 1 
2019/2020 Complete Design and Approvals 
Nov 2020 Commence construction
June 2021  Project completion

 

Project Update

The Innisfail Turf Club Course Proper rectification works was completed between December 2020 to June 2021. The project cost roughly $500,000 to complete.