- Home
- Infrastructure
- Country & Regional Infrastructure
- Longreach Jockey Club

Longreach Jockey Club
Completed
Start date
June 2019
Estimated completion date
March 2021
Cost
$82,000
Location
Longreach Jockey Club
Under CRP Round 1 the Longreach Jockey Club were successful in obtaining funding for the replacement of their existing judge’s tower.
Project Timeline
| Year | Action |
|---|---|
| June 2019 | CRP Funding Approval – Round 1 |
| 2019/2020 | Complete Design and Approvals |
| Jan 2021 | Commence construction |
| March 2021 | Project completion |
Project Update
The construction works were completed in early March 2021 and has been used for multiple race meetings this year.