Bundaberg Greyhound Racing Club
CommencedBundaberg Straight track project
Racing at Bundaberg ceased in September 2024, after the racing surface was deemed unsuitable for ongoing racing.
Racing Queensland (RQ) is progressing plans to redevelop the venue through the Racing Infrastructure Fund. Following market testing, significant cost and contractor challenges required the project scope to be reviewed, with updated designs and cost estimates obtained for alternative track configurations.
In June 2026, RQ hosted an industry forum in Bundaberg to provide a project update and hear directly from local participants and stakeholders.
The current proposal is for a straight track with a minimum length of 350m, including 300m and 350m starts and going from grass to sand. The Bundaberg Project Control Group, comprising RQ and invited Bundaberg representatives, is also investigating whether a longer straight track and additional starting distances can be delivered.
The Project Control Group will consider all aspects of the track and supporting infrastructure, including the lure system and access to and from the starting boxes. Industry consultation will continue as the project progresses.
Bundaberg Greyhound Track concept design consultation
Racing Queensland is seeking industry feedback on the proposed Bundaberg Greyhound Track concept design.
View the concept designs and share your feedback through the online form here.
Please read the Bundaberg Straight Track FAQ document for more information about the proposed redevelopment, track design, racing opportunities and indicative project timeline.
Planned Project timeline
Year | Action |
|---|---|
Oct - Nov 2026 | Detailed design |
Late 2026 | Development approval |
Nov 2026 - Mar 2027 | Procurement |
Apri - Nov 2027 | Commence construction |
Late 2027 - Early 2028 | Track trials preparation |